摘 要:輕型井點(diǎn)降水法比較廣泛使用于基坑降水工程,通過(guò)降水施工可將基坑的原地下水位降至基坑坑底以下,使基坑保持干燥狀態(tài),從而可以改善施工條件,保證基坑的穩(wěn)定和安全。本文主要從工藝原理、施工方法、質(zhì)量要求等方面敘述了人工沖孔輕型井點(diǎn)在太倉(cāng)市規(guī)劃館工程基坑降水工程中的應(yīng)用。
關(guān)鍵詞:人工;井點(diǎn); 基坑; 降水
Manual punching light well point in the foundation pit dewatering engineering
Zhong Qinggan
( Suzhou construction engineering supervision company, Jiangsu Suzhou 215129 )
Abstract: the light well point precipitation method widely used in foundation pit engineering, through construction foundation pit precipitation may be the original underground water level to the foundation pit excavation bottom following, keep dry state, which can improve the construction conditions, guarantee the stability and safety of foundation pit. This article mainly from the technological principle, construction method, quality requirements and other aspects of artificial punching light well point in Taicang city planning exhibition hall engineering dewatering of foundation pit engineering.
Key words: artificial well point dewatering of foundation pit
太倉(cāng)市規(guī)劃館工程位于太倉(cāng)市南郊科教新城江申大道、平治路交叉處,天鏡湖的西南側(cè),總建筑面積18545平方米。規(guī)劃館主館地上三層、地下一層;地下一層(汽車(chē)庫(kù)、設(shè)備用房)、地上三層(中間設(shè)有三層通高的中庭,一層為中心模型展區(qū);二層為專(zhuān)項(xiàng)成果展示區(qū);三層為人防展區(qū)和展館內(nèi)辦公區(qū));
該工程主館設(shè)計(jì)為一層地下室,基坑實(shí)際開(kāi)挖深度為2.9m,雖然沒(méi)有達(dá)到住房和城鄉(xiāng)建設(shè)部《關(guān)于印發(fā)〈危險(xiǎn)性較大的分部分項(xiàng)工程安全管理辦法〉的通知》(建質(zhì)[2009]87號(hào))文件規(guī)定的深基坑標(biāo)準(zhǔn),但由于到工程建在天鏡湖的湖畔,而且60%的施工區(qū)域都是回填而成的,為防止基坑開(kāi)挖后湖水的滲入,施工總承包單位對(duì)本工程基坑的施工考慮了雙軸攪拌樁止水帷幕結(jié)合人工沖孔輕型井點(diǎn)降水、邊坡掛網(wǎng)噴漿的施工工藝。
根據(jù)本工程的土層情況及開(kāi)挖深度分析,本工程的地下室基礎(chǔ)在地質(zhì)報(bào)告標(biāo)注的第三層土下部,該土層的土質(zhì)大多為灰色粉質(zhì)土,流塑性,含水量較高(W=42%),孔隙比大(e=1.2左右),土的強(qiáng)度低,靈敏度高,滲透性較差,加之基坑底以下的第四層為正是地下水含量最豐富的一層,這給降水帶來(lái)了一定的難度,為了保證基坑的干燥度及邊坡的穩(wěn)定性,根據(jù)理論計(jì)算及設(shè)計(jì)的要求,結(jié)合本工程降水要求的特點(diǎn),確定選用人工沖孔井點(diǎn)降水,來(lái)降低本工程的地下水位,從而達(dá)到保持坑底干燥,便于施工,滿(mǎn)足基礎(chǔ)工程施工的要求。
1.人工沖孔輕型井點(diǎn)的工藝原理
1.1 在基坑開(kāi)挖施工中,為了避免產(chǎn)生流砂、管涌,防止基坑坑壁土體的坍塌,保證施工安全和工程質(zhì)量,一般盡量避免在水下作業(yè)。當(dāng)?shù)叵滤桓哂诨用鏁r(shí),應(yīng)進(jìn)行基坑降水。
1.2太倉(cāng)市規(guī)劃館工程的基坑人工沖孔輕型井點(diǎn)降水原理系在基坑外圍、雙軸攪拌樁止水帷幕的內(nèi)側(cè)埋設(shè)井點(diǎn)管深入含水層內(nèi),每?jī)蓚€(gè)井點(diǎn)管的上端通過(guò)連接彎管與離心式自吸泵相連,離心式自吸泵再與集水總管連接,啟動(dòng)抽水離心式自吸泵后,地下水便在離心式自吸泵吸力的作用下,經(jīng)井點(diǎn)管外側(cè)濾水層進(jìn)入井點(diǎn)管,由離心式自吸泵抽入集水總管排出坑外,由此使地下水位降低到基坑底以下。
1.3根據(jù)人工沖孔輕型井點(diǎn)在太倉(cāng)市規(guī)劃館工程基坑降水應(yīng)用的情況來(lái)看,該施工工藝具有機(jī)具設(shè)備簡(jiǎn)單、操作方便、降水效果好等特點(diǎn),能夠有效地提高基坑邊坡的穩(wěn)定性、防止坑底流砂現(xiàn)象的發(fā)生。特別適用于滲透系數(shù)為 0.1~5.0m/d 的土層及含有大量的細(xì)砂和粉砂的土層,亦適用于明溝排水易引起流砂、塌方的基坑降水施工。
2.人工沖孔輕型井點(diǎn)的施工方法
2.1材料要求
2.1.1沖孔管
沖孔管為2m~2.5m長(zhǎng)、直徑為32mm 鋼管,下端為帶有5㎜~10㎜孔錐形管尖,上端連接沖孔管直徑相匹配的塑料軟管(或膠皮管),塑料軟管(或膠皮管)的長(zhǎng)度根據(jù)實(shí)際需要配置;
2.1.2井點(diǎn)管
井點(diǎn)管為2m長(zhǎng)、直徑為25mm的聚乙烯PE管,下端1m長(zhǎng)范圍內(nèi)鉆Ф5mm梅花形孔(間距100 mm),鉆孔的部位及管的下端包尼龍窗紗二層,用12號(hào)鐵絲將尼龍窗紗繞緊,上端用聚乙烯PE管連接管與水泵連接。
2.1.3連接管
連接管為直徑25mm的聚乙烯PE管,用于井點(diǎn)管和水泵、水泵和集排水管之間的連接。
2.1.4 集排水管
集排水管為直徑40㎜~50㎜聚乙烯PE管,水泵和集排水管之間用連接管采用三通接頭與集排水管相連。endprint
2.2主要機(jī)具
2.2.1 離心式自吸泵
井點(diǎn)抽水用CPM158離心泵,每?jī)蓚€(gè)井點(diǎn)共用一臺(tái)水泵。CPM158離心泵是一種高效家用水泵。它由微電機(jī)、離心泵和高質(zhì)量的特殊機(jī)械密封組成,具有重量輕、耗電省、操作和維修方便,安全可靠等優(yōu)點(diǎn)。其性能參數(shù)見(jiàn)下表:
2.2.2 高壓水泵
100TSW-7高壓離心泵,配備一個(gè)壓力表,作下井管之用;
2.3 施工工藝
2.3.1根據(jù)地質(zhì)勘探報(bào)告?zhèn)渥⒌牡叵滤簧疃?、土的滲透系數(shù)和土質(zhì)分布情況確定降水方案;
2.3.2井點(diǎn)布置根據(jù)基坑平面形狀與大小、地質(zhì)和水文情況、工程性質(zhì)、降水深度等而定。本工程主館基坑井點(diǎn)采用環(huán)形井點(diǎn),平臺(tái)區(qū)沿湖側(cè)采用單排井點(diǎn),井點(diǎn)管距坑壁不大于 0.50m,井點(diǎn)的間距為1.5m,埋深1.5m。應(yīng)優(yōu)先采用擋水作用的支護(hù)結(jié)構(gòu),如深層攪拌樁、鋼板樁、砼灌注樁或地下連續(xù)墻等,并盡可能把降水井點(diǎn)立管埋設(shè)在支護(hù)墻的內(nèi)側(cè)(基坑一側(cè)),井點(diǎn)管的深度應(yīng)淺于支護(hù)的深度。(注:本工程就是采用雙軸攪拌樁支護(hù)兼止水帷幕(樁長(zhǎng)8 m)結(jié)合人工沖孔輕型井點(diǎn)降水、邊坡按照1:1.25放坡掛網(wǎng)噴漿的施工工藝。)
2.3.3 井點(diǎn)管施工工藝程序是:放線定位→土方預(yù)開(kāi)挖→沖孔→安裝井點(diǎn)管→安裝離心式自吸泵→用彎聯(lián)管將井點(diǎn)管與水泵連接→安裝集排水管→開(kāi)動(dòng)離心水泵抽水→觀測(cè)地下水位變化。
2.3.4井點(diǎn)沖孔,人工將沖孔管對(duì)準(zhǔn)井點(diǎn)位置,啟動(dòng)高壓水泵,水壓控制在0.4~0.8MPa,在高壓水沖擊下沖孔管開(kāi)始下沉,并不斷地升降沖孔管。在射水與沖孔管沖切作用下,大約在5~10min時(shí)間之內(nèi),沖孔管可下沉2m左右,若遇到較厚的純粘土?xí)r,沉管時(shí)間要延長(zhǎng),此時(shí)可增加高壓水泵的壓力,以達(dá)到加速沉管的速度。沖擊孔的成孔直徑應(yīng)達(dá)到100~150mm,保證井孔壁與井點(diǎn)管之間有一定間隙,以便于填充砂石,沖孔深度應(yīng)比濾管設(shè)計(jì)安置深度低500mm以上,當(dāng)基坑附近沒(méi)有建筑、管線、道路時(shí),坑中井點(diǎn)水位應(yīng)降至基坑底面以下1米為宜。
2.3.5井點(diǎn)管埋設(shè)沿
成孔后將井點(diǎn)管插入井孔,使井點(diǎn)管露出地面500mm,然后沿井孔壁與井點(diǎn)管之間倒入粒徑5-15mm瓜子片,使管底有500mm高,再沿井點(diǎn)管四周均勻投放2-4mm粒徑粗砂,上部1.0m深度內(nèi),用粘土填實(shí)以防漏氣。
2.3.6 離心式自吸泵安裝
井點(diǎn)管埋設(shè)完畢后,進(jìn)行離心式自吸泵的安裝,每?jī)筛c(diǎn)管用三通與一臺(tái)離心式自吸泵,水泵和集排水管采用連接管接通。
2.3.7設(shè)備調(diào)試
井點(diǎn)管、連接管、水泵、集排水管等部件連接完畢后,即可接通電源進(jìn)行試抽水,檢查有無(wú)漏氣、淤塞情況,出水是否正常。井點(diǎn)使用時(shí),正常出水規(guī)律是“先大后小,先渾后清”,如不上水、或水一直較渾,或出現(xiàn)清后又渾等情況,應(yīng)立即檢查、檢修后方可使用。
2.3.8 基坑降水
井點(diǎn)使用時(shí),應(yīng)保持離心式自吸泵連續(xù)不間斷抽水。一般連續(xù)抽水3d~5d后,基坑形成地下降水漏斗,地下水位降落、基本趨于穩(wěn)定,即可進(jìn)行基礎(chǔ)和地下構(gòu)筑物的施工。井點(diǎn)降水時(shí),應(yīng)對(duì)水位降低區(qū)域內(nèi)的建筑物進(jìn)行沉降觀測(cè),發(fā)現(xiàn)有沉陷或水平位移過(guò)大時(shí),應(yīng)及時(shí)采取防護(hù)技術(shù)措施。
2.3.9 井點(diǎn)拆除
基礎(chǔ)和地下構(gòu)筑物的施工完成后,可以停止降水并拆除井點(diǎn)系統(tǒng)。井點(diǎn)管的拔出可借助于機(jī)械,比如挖掘機(jī)、神仙葫蘆等。井點(diǎn)管拔出所留孔洞用砂或土堵塞。
3.人工沖孔輕型井點(diǎn)的施工質(zhì)量要求
3.1 井點(diǎn)管間距、埋設(shè)深度應(yīng)符合“基坑支護(hù)與降水工程專(zhuān)項(xiàng)方案”要求,井點(diǎn)管濾水管部分必須埋入含水層內(nèi)。
3.2井點(diǎn)成孔后,應(yīng)立即下井點(diǎn)管并填入瓜子片、中粗砂濾料,以防塌孔。不能及時(shí)下井點(diǎn)管時(shí),孔口應(yīng)蓋蓋板,防止物件掉入井孔內(nèi)堵孔。井點(diǎn)埋設(shè)應(yīng)無(wú)嚴(yán)重漏氣、淤塞、出水不暢等情況。
3.3降水期間,現(xiàn)場(chǎng)設(shè)專(zhuān)人經(jīng)常觀測(cè),若抽水過(guò)程中發(fā)現(xiàn)真空度不足,應(yīng)立即檢查整個(gè)抽水系統(tǒng)有無(wú)漏氣環(huán)節(jié),并應(yīng)及時(shí)排除。
3.4 在抽水過(guò)程中,特別是開(kāi)始抽水時(shí),應(yīng)檢查有無(wú)井點(diǎn)管被淤塞的情況,可通過(guò)管內(nèi)水流聲、管子表面是否潮濕等方法進(jìn)行檢查。如果井點(diǎn)管被淤塞數(shù)量超過(guò)井點(diǎn)管總數(shù)的10%,則會(huì)嚴(yán)重影響基坑降水效果,應(yīng)及時(shí)采取措施,采用高壓水反復(fù)沖洗處理。
3.5井點(diǎn)使用后,中途不得停泵,防止因停止抽水使地下水位上升,造成淹泡基坑的事故.另外,在基坑土方開(kāi)挖后,應(yīng)保持降低地下水位在基底0.5m以下,以防止地下水?dāng)_動(dòng)地基土體。
4.結(jié)束語(yǔ)
輕型井點(diǎn)降水法是一種行之有效地處理軟弱土地基的處理方法,已被廣泛應(yīng)用,施工工藝已經(jīng)很成熟。本文所述人工沖孔輕型井點(diǎn)降水的施工方法較傳統(tǒng)的井點(diǎn)降水法相比,更具有施工工藝簡(jiǎn)單、易操作、降水效果好等特點(diǎn),該工藝在太倉(cāng)市規(guī)劃館工程中對(duì)規(guī)劃館主館基坑降水應(yīng)用情況來(lái)看,該施工方法對(duì)處理地下水位高、土壤含水率較大的地基,不僅起到了增加邊坡的穩(wěn)定性,而且可以大大減少土方開(kāi)挖量,既保證了安全施工,又能大大降低施工的成本,同時(shí)可以縮短施工工期。
【文章編號(hào)】1006-2688(2017)10-0021-03endprint