• 
    

    
    

      99热精品在线国产_美女午夜性视频免费_国产精品国产高清国产av_av欧美777_自拍偷自拍亚洲精品老妇_亚洲熟女精品中文字幕_www日本黄色视频网_国产精品野战在线观看

      ?

      工程合同譯評(20)FIDIC文本“變更和調(diào)整”條款(上)

      2020-02-26 19:11:23/
      建筑 2020年15期
      關鍵詞:承包人變動條款

      文 / 李 健

      在工程建設實踐中,變更是施工合同履行過程中的常見現(xiàn)象,變更也是導致對合同價格進行調(diào)整的重要因素。鑒于合同變更和調(diào)整極易引發(fā)合同履行障礙或爭議,合同關于變更和調(diào)整的約定具有重要意義。今天我們來討論FIDIC1999施工合同文本 Conditions?of?Contract?for?Construction 中的 13.?Variations?and?Adjustment“13變更和調(diào)整”條款。

      原文1:13.1 Right to Vary

      Variations?may?be?initiated?by?the?Engineer?at?any?time?prior?to?issuing?the?Taking-Over?Certificate?for?the?Works,?either?by?an?instruction?or?by?a?request?for?the?Contractor?to?submit?a?proposal.

      The?Contractor?shall?execute?and?be?bound?by?each?Variation,?unless?the?Contractor?promptly?gives?notice?to?the?Engineer?stating?(with?supporting?particulars)?that?the?Contractor?cannot?readily?obtain?the?Goods?required?for?the?Variation.?Upon?receiving?this?notice,?the?Engineer?shall?cancel,?confirm?or?vary?the?instruction.

      Each?Variation?may?include:

      (a)?changes?to?the?quantities?of?any?item?of?work?included?in?the?Contract?(however,?such?changes?do?not?necessarily?constitute?a?Variation),

      (b)?changes?to?the?quality?and?other?characteristics?of?any?item?of?work,

      (c)?changes?to?the?levels,?positions?and/or?dimensions?of?any?part?of?the?Works,

      (d)?omission?of?any?work?unless?it?is?to?be?carried?out?by?others,

      (e)?any?additional?work,?Plant,?Materials?or?services?necessary?for?the?Permanent?Works,?including?any?associated?Tests?on?Completion,?boreholes?and?other?testing?and?exploratory?work,?or

      (f)?changes?to?the?sequence?or?timing?of?the?execution?of?the?Works.

      The?Contractor?shall?not?make?any?alteration?and/or?modification?of?the?Permanent?Works,?unless?and?until?the?Engineer?instructs?or?approves?a?Variation.

      試譯:13.1 變更權

      在頒發(fā)工程接收證書前的任何時間,工程師可以通過發(fā)布指示或以要求承包人提交建議書的方式提出變更。

      承包人應當執(zhí)行每項變更并受其約束,除非承包人立即向工程師發(fā)出通知,說明承包人難以取得變更所需的物件(須附具體證明資料)。接到通知后,工程師應當取消、確認或修改指示。

      每項變更可以包括:

      (1)合同中任何子項工作內(nèi)容數(shù)量的改變(此類改變并不當然構成變更);

      (2)任何子項工作質(zhì)量或其他特性的改變;

      (3)工程任何部位標高、位置或尺寸的改變;

      (4)任何工作的省略,但將交由他人完成的除外;

      (5)任何額外附加的永久工程所需的工作、設備、材料或服務,包括任何相關的竣工檢驗、鉆孔和其他試驗及勘探工作;

      (6)工程的實施順序或時間安排的改變。

      除非工程師發(fā)出指示或批準變更,在此之前,承包人不得對永久工程作任何改動或修改。

      點評:1.這里“變更權Right?to?Vary”子款內(nèi)容很豐富,具體涉及:第一,誰有權行使變更權發(fā)起initiate變更:the?Engineer;第二,變更權行使的時間有何限制:at?any?time?prior?to?issuing?the?Taking-Over?Certificate?for?the?Works;第三,行使變更權的方式:either?by?an?instruction?or?by?a?request?for?the?Contractor?to?submit?a?proposal;第四,變更對承包人的約束力:The?Contractor?shall?execute?and?be?bound?by?each?Variation;第五,承包人的通知對變更的阻斷:Upon?receiving?this?notice,?the?Engineer?shall?cancel,?confirm?or?vary?the?instruction;第六,變更的內(nèi)容涉及范圍;第七,無變更情況下,對承包人變動永久工程的限制。

      2.什么是“Variation變更”?事實上,在FIDIC文本中,這是一個通過外延來定義的概念:1.1.6.9?“Variation”?means?any?change?to?the?Works,?which?is?instructed?or?approved?as?a?variation?under?Clause?13?[Variations?and?Adjustments]?。也就是說,“變更”是指對工程的任何變動,這些變動是按照第13條[變更和調(diào)整]被指示或批準作為變更的。注意,這里特別強調(diào)是對“工程”的任何變動,而不是對合同條款或合同權利義務的變動,雖然在建設工程合同中,對“工程”的任何變動通常會引起對合同權利義務的變動。在合同法意義上的合同“變更”通常用語是modify或modification。中國《民法典》第543條規(guī)定,“當事人協(xié)商一致,可以變更合同”,The?parties?may?modify?a?contract?where?they?reach?a?consensus?through?consultation。合同“變更”modify或modification,是“雙方合意”的結果。

      3.只有理解到“Variation變更”是對“工程”的任何變動,我們才能體會到“Variation變更”不當然是“雙方合意”的結果。除非工程師的權限在專用條款中另有限制,本條款將變更權主要直接賦予監(jiān)理工程師the?Engineer(其代表發(fā)包人或業(yè)主the?Employer),而沒有對等地賦予承包人。一項變動change構成一項“Variation變更”,無需承包人同意,但卻可以約束承包人The?Contractor?shall?execute?and?be?bound?by?each?Variation。如果承包人認為,工程師所指示的變更既不必要necessary也不適宜appropriate,除非立即向工程師發(fā)出通知說明自己難以取得變更所需的物件(須附具體證明資料)unless?the?Contractor?promptly?gives?notice?to?the?Engineer?stating?(with?supporting?particulars)?that?the?Contractor?cannot?readily?obtain?the?Goods?required?for?the?Variation,便只能通過爭議解決條款來質(zhì)疑工程師的指示。

      4.關于變更范圍中,changes?to?the?quantities?of?any?item?of?work?included?in?the?Contract?(however,?such?changes?do?not?necessarily?constitute?a?Variation),通常認為是工程量清單中數(shù)量的簡單變化。如果數(shù)量變化較大,且符合FIDIC第12.3款[估價]相關約定,則會引起適用新的單價或價格。

      原文2:13.2 Value Engineering

      The?Contractor?may,?at?any?time,?submit?to?the?Engineer?a?written?proposal?which?(in?the?Contractor’s?opinion)?will,?if?adopted,?(i)?accelerate?completion,?(ii)?reduce?the?cost?to?the?Employer?of?executing,?maintaining?or?operating?the?Works,?(iii)?improve?the?efficiency?or?value?to?the?Employer?of?the?completed?Works,?or?(iv)?otherwise?be?of?benefit?to?the?Employer.

      The?proposal?shall?be?prepared?at?the?cost?of?the?Contractor?and?shall?include?the?items?listed?in?Sub-Clause?13.3?[Variation?Procedure].

      If?a?proposal,?which?is?approved?by?the?Engineer,?includes?a?change?in?the?design?of?part?of?the?Permanent?Works,?then?unless?otherwise?agreed?by?both?Parties:

      (a)?the?Contractor?shall?design?this?part,

      (b)?sub-paragraphs?(a)?to?(d)?of?Sub-Clause?4.1?[Contractor’s?General?Obligations]?shall?apply,?and

      (c)?if?this?change?results?in?a?reduction?in?the?contract?value?of?this?part,?the?Engineer?shall?proceed?in?accordance?with?Sub-Clause?3.5?[Determinations]?to?agree?or?determine?a?fee,?which?shall?be?included?in?the?Contract?Price.?This?fee?shall?be?half?(50%)?of?the?difference?between?the?following?amounts:

      (i)?such?reduction?in?contract?value,?resulting?from?the?change,?excluding?adjustments?under?Sub-Clause?13.7?[Adjustments?for?Changes?in?Legislation]?and?Sub-Clause?13.8?[Adjustments?for?Changes?in?Cost],?and

      (ii)?the?reduction?(if?any)?in?the?value?to?the?Employer?of?the?varied?works,?taking?account?of?any?reductions?in?quality,?anticipated?life?or?operational?efficiencies.

      However,?if?amount?(i)?is?less?than?amount?(ii),?there?shall?not?be?a?fee.

      試譯:13.2 價值工程

      承包人可以隨時向工程師提交一份書面建議,只要在其看來,如果該建議被采用,可以(1)加速完工,(2)降低業(yè)主實施、維護或運行工程的成本,(3)為業(yè)主提高竣工工程的效率或價值,或(4)為業(yè)主帶來其他利益。

      此類建議書由承包人自費編制,并應當包含第13.3款[變更程序]所列條目。

      如果一項建議包含了對部分永久工程設計的改變,且該項建議已由工程師批準,除非雙方另有協(xié)議,否則:

      (1)承包人應當設計該部分工程;

      (2)第4.1款[承包人的一般義務]?①至④段將適用;

      (3)如果此項改變導致該部分工程的合同價值減少,工程師應當依據(jù)第3.5款[確定],商定或決定一項費用并加入合同價格。此項費用應當是下列金額之差的一半(50%):

      ①由此改變引起的合同價值的減少,不包括依據(jù)第13.7款[因法律改變的調(diào)整]和第13.8款[因成本改變的調(diào)整]所作的調(diào)整;

      ②變更后的工程由于質(zhì)量、預期壽命或運行效率的降低引起的對業(yè)主價值上的減少(如果有)。

      但是,如果①中的金額少于②中的金額,則不考慮該項費用。

      點評:1.前面已經(jīng)說過,除非工程師的權限在專用條款中另有限制,條款13.1?Right?to?Vary將變更權主要直接賦予監(jiān)理工程師the?Engineer,而沒有對等地賦予承包人;但這并不是說,不考慮承包人的能動履行合同的積極性。承包人可以通過提出建議 submit?to?the?Engineer?a?written?proposal的方式,經(jīng)由工程師批準,達到“變更Variation”的實際效果。因此本款可以認為是承包人主動引發(fā)變更程序啟動的規(guī)定。

      2.對承包人能動履行合同積極性的鼓勵機制在于:要求“變更”有利于業(yè)主利益,同時,也要照顧承包人的利益。這有點類似中國工程實踐中的“節(jié)約分成”。如果一項建議包含了對部分永久工程設計的改變,且該項建議已由工程師批準,通常情況下,若此項改變導致該部分工程合同價值減少,工程師應當依據(jù)合同商定或決定一項費用并加入合同價格。

      猜你喜歡
      承包人變動條款
      性侵未成年人新修訂若干爭議條款的理解與適用
      北上資金持倉、持股變動
      北向資金持倉、持股變動
      南向資金持倉、持股變動
      正確審視“紐約假期”條款
      中國外匯(2019年15期)2019-10-14 01:00:48
      On Knock-for-Knock Principle:Analysis of SUPPLYTIME 2017 Clause 14(a)
      律師解疑
      變動的是心
      關于《合同法》中“主體結構由施工總承包人自行完成”之規(guī)定的探討
      制定一般反濫用條款:達成平衡
      灵山县| 四会市| 呼和浩特市| 宝清县| 正蓝旗| 湖北省| 贞丰县| 黄龙县| 沁阳市| 乐清市| 西华县| 潮安县| 灵武市| 屏山县| 贵南县| 含山县| 齐河县| 寿光市| 萍乡市| 兴山县| 大渡口区| 江川县| 大余县| 扎赉特旗| 琼结县| 靖边县| 静海县| 六枝特区| 博客| 崇阳县| 五河县| 兰坪| 房产| 文昌市| 商丘市| 蕲春县| 新蔡县| 广昌县| 乡城县| 化德县| 丹东市|